Report One, May 14, 2013   •   Capital South Campus Center   •   20 Warren St. Albany, NY

City Streets: Good   •   Site Conditions: Dry   •   Purpose: Scheduled inspections   •   Photographs: Below   •   Inspector: Robert Becker

4/29/13

  • After site clearing and preliminary staging areas were prepared building line E was excavated.
  • Clay mixed with ashes and miscellaneous debris was encountered

5/06/13

  • Excavations continued to complete building foot print pile cap sub grade.
  • Materials encountered were consistent with pre construction soils investigations.

5/07/13

  • View from 3 Lincoln Square indicating geotextile fabric and crushed stone base material.

5/8/13

  • Completed excavation and stone base ready for driven pile operations

Short term schedule:

  • Commence pile driving (test piles) 5/15 to 5/17
  • Dynamic testing 5/18
  • Pile driving 5/20 through 6/7
 